New End Date for Willow Creek Rd Micro Seal Project

3/29/24

It appears completion of the Willow Creek Road micro seal project will take a little longer than expected. The original end date for the project was late April. Now, City of Prescott officials say all micro seal work will be finished in late May. Crews are working between Iron Springs Road and the Green Lane/Pulliam Drive intersection.

Motorists traveling through the area may encounter lane restrictions, reduced speeds, rough road conditions, and flaggers directing traffic. Work hours are 7 a.m. to 4 p.m. for the northbound lanes and 9 a.m. to 8 p.m. for the southbound lanes Monday through Friday.

The goals of the project are to fill in cracks in the asphalt and extend the life of the roadway.