4/3/24
Micro seal work on Willow Creek Road continues this week. Crews are working between Iron Springs Road and the Green Lane/Pulliam Drive intersection. One lane of traffic will be open at all times in the work zone. Micro milling, which involves the removal of the thin layer of existing pavement, has been completed. Crack sealing work should be finished this week. Next week, the micro seal will be applied to the roadway.
Work hours are 7 a.m. to 4 p.m. on the northbound lanes and 9 a.m. to 8 p.m. on the southbound lanes. The project should be completed sometime around the end of May.