Crews have finished installing new curbs, gutters, and sidewalks at the intersection of Prescott Lakes Parkway and Sundog Ranch Road. Asphalt paving operations in the work zone are now underway. In addition, electrical work is being performed for the installation of a new traffic signal. Motorists traveling through the area may encounter lane restrictions, rough road conditions, reduced speeds, and flaggers directing traffic.
Work hours are 7 a.m. to 6 p.m. weekdays. The project should be finished sometime this spring.